Pad Construction - Day 44

›
It was day 2 of installing the cellars on the well pad. All six of the holes dug yesterday now contain a large pipe, the form for the concre...
11 May 2011

Pad Construction - Day 43

›
Another clear, dry day and the non-stop hauling of rock to the pad area continues On the well pad a base layer of mixed sized rock is spread...
10 May 2011

Two day old Killdeer Chicks

›
I was heading to our pond this morning to check on the nesting waterfowl when I spotted two adult killdeer and at least three chicks. The ad...

Waitting Goose

›
With today's warm weather the goose took some time off the nest for lunch and a quick swim. She has been sitting on the eggs for at leas...

Pad Construction - Day 42

›
Greenway Engineering was at the site today surveying locations on the well pad. They set up a GPS base station along Joyce Road at a know p...
09 May 2011

Pad Construction - Day 41

›
A clear, dry day and work continued on the well pad. More stone was dumped on the access road from the stream crossing to the pad area. Truc...
08 May 2011

Killdeer Chicks

›
While checking the killdeer nest today I noticed the bird was acting different than on my past visits to the nest. On closer inspection of t...

Pad Construction - Day 40

›
After yesterday's activity, today was quiet and no one was on the site.
07 May 2011

Wood Duck Nest

›
While checking on the nesting goose at the pond I noticed a couple clumps down feathers near one of the nesting boxes. I had placed the nest...

Pad Construction - Day 39

›
Activity at the site picked up today as a large crew of workers were on site to replace the existing silt fence, along the downhill (west) s...
5 comments:
06 May 2011

Pad Construction - Day 38

›
After yesterday's activity of hauling stone to the pad area, today was a quiet day. A large area of the pad has been covered with stone...
1 comment:
05 May 2011

Pad Construction - Day 37

›
After a rain out yesterday the crew was back and rock was being hauled to the pad area. Six trucks lined up at the stream crossing waiting t...
‹
›