
Topsoil from the stockpile is hauled to the west side of the site, above the silt socks, and the dozer with GPS grades the topsoil back to original grade.

With the topsoil on the south end of the site dried out and finish grade complete, the hydroseeding of the south end started today.

The west side of the site after hydroseeding.

No comments:
Post a Comment