05 May 2011

Pad Construction - Day 37

After a rain out yesterday the crew was back and rock was being hauled to the pad area. Six trucks lined up at the stream crossing waiting their turn to unload.



As one truck climbs the hill to the pad another truck leaves and six trucks wait.



This truck was able to climb the hill, but ...



some trucks needed a little push to make the hill.



Once on the pad area the trucks quickly dumped their loads.



At the south end of the pad a drainage ditch was being installed.



Yesterday's rain left the northeast corner of the pad underwater.



Draining water from the northeast corner of the pad.