08 June 2012

Pipeline Construction

With the hydrostatic testing of the Wesauking pipeline complete, the frac tanks used for water storage were removed toady.



A crew works on re-installing the check valve (yellow section of pipe) that was removed during the hydrostatic test. The check valve controls the directional flow of gas on the Wesauking Pipeline and prevents gas from flowing the 24 inch Wilmot Pipeline into the 12 inch Wesauking Pipeline.



Workers from Chesapeake monitor the 24 inch "pig launcher" on the Wilmot Pipeline.