Today's temperature was much milder than the past week's and the roofers were busy laying shingles on Brian & Tish Hopkins' new house.
By the afternoon the temperature was in the low 30's and the roofers were done for the day. It looks like they may have come up a few bundles of shingles short. The top section of the south roof is missing a few rows of shingles and some of the ridge cap is still needing shingles.
A view of the back side of the house.
31 January 2014
30 January 2014
Hopkins' New House - Day 8
The sky was clear, the wind was calm, but the morning temperature was -2 degrees F. as the roofing crew started working on Brian & Tish Hopkins' new house.
By 11:00PM the temperature was in the teens and a large section of the roof on the back side (sunny side) of the house was shingled.
By 4:00PM the crew was attaching the ridge vent on sections of the house.
As the afternoon sun started to set, the temperature was in the mid-20's and the crew had completed large sections of the roof.
By 11:00PM the temperature was in the teens and a large section of the roof on the back side (sunny side) of the house was shingled.
By 4:00PM the crew was attaching the ridge vent on sections of the house.
As the afternoon sun started to set, the temperature was in the mid-20's and the crew had completed large sections of the roof.
24 January 2014
Hopkins' New House - Day 7
The temperature dropped to 0 degrees F. overnight and by 10:30AM the frost was still clinging to the roof on Brian & Tish Hopkins' new house. The cold weather didn't slow the framing crew as they finished installing the window in the house.
A view of the back side of the house showing the windows, which had been added, along with the ledger board for a deck (a project for Brian to work on).
All the interior walls have been installed and metal brackets are attached to secure the walls to the roof rafters.
Other than installing the entrance doors, which are scheduled to be installed later, the crew was done with all of their work by 2:30PM on the seventh day of framing.
A view of the temporary stairs to the second floor from the front entrance .
A view looking from the den to the living room.
The second floor master bedroom with walk-in closet.
Master bathroom.
A view of the back side of the house showing the windows, which had been added, along with the ledger board for a deck (a project for Brian to work on).
All the interior walls have been installed and metal brackets are attached to secure the walls to the roof rafters.
Other than installing the entrance doors, which are scheduled to be installed later, the crew was done with all of their work by 2:30PM on the seventh day of framing.
A view of the temporary stairs to the second floor from the front entrance .
A view looking from the den to the living room.
The second floor master bedroom with walk-in closet.
Master bathroom.
23 January 2014
Hopkins' New House - Day 6
There wasn't any activity at Brian & Tish Hopkins' new house yesterday due to the cold weather but the framing crew was back today. More building materials arrived today, including bundles of roofing shingles which were stacked in the roof awaiting a roofing crew.
By 1:00PM the temporary stairs were installed to make access the second floor easier.
Interior walls on the second floor were going in but there was still some open space at 1:00PM.
By 4:30PM most of the second floor walls were in place.
The room layouts are starting to take shape as the tub and shower units are positioned in the rough openings.
A stack of wall studs in one of the front bedrooms dwindles as the new walls go up.
The windows are starting to go in.
By 1:00PM the temporary stairs were installed to make access the second floor easier.
Interior walls on the second floor were going in but there was still some open space at 1:00PM.
By 4:30PM most of the second floor walls were in place.
The room layouts are starting to take shape as the tub and shower units are positioned in the rough openings.
A stack of wall studs in one of the front bedrooms dwindles as the new walls go up.
The windows are starting to go in.
21 January 2014
Hopkins' New House - Day 5
The weather turned colder over night and there was a light dusting of snow but the framing crew didn't slow down on the construction of Brian & Tish Hopkins' new house.
By 11:00AM they had installed more roof rafters and sheathing on the front side of the house.
Roof framing on the north end of the house at 11:00AM.
By 4:00PM the crew had finished the roof framing and some more of the interior walls.
By 11:00AM they had installed more roof rafters and sheathing on the front side of the house.
Roof framing on the north end of the house at 11:00AM.
By 4:00PM the crew had finished the roof framing and some more of the interior walls.
20 January 2014
Hopkins' New House - Day 4
The weekend brought a couple inches of snow and the framing crew was busy working on Brian & Tish Hopkins' new house
Today is the forth day of work by the framing crew and by 10:00AM they had the second floor exterior walls in place and ready to start on the roof.
The colder weather over the weekend firmed up the ground and some rough grading was done to prepare for a crane and trucks of roof trusses.
By 4:00PM the roof trusses were in place and the crew was installing the roof sheathing.
A view of the back side of the house with roof sheathing installed.
Today is the forth day of work by the framing crew and by 10:00AM they had the second floor exterior walls in place and ready to start on the roof.
The colder weather over the weekend firmed up the ground and some rough grading was done to prepare for a crane and trucks of roof trusses.
By 4:00PM the roof trusses were in place and the crew was installing the roof sheathing.
A view of the back side of the house with roof sheathing installed.
17 January 2014
Hopkins' New House - Day 3
It's now the third day of framing construction on Brian & Tish Hopkins' new house and the crew is busy working on the second floor. By 10:00AM they have installed the section of the second floor over the front porch, some of the sub-floor and the back exterior wall.
View of the back side of the house in the morning.
A crane was brought in to lift a heavy steel I-beam and position it in the garage area.
Setting the I-beam in place. This I-beam spans the length of the garage area and will support the second floor living space over the garage.
With the I-beam in place the crew installed the floor joists for the second floor. The garage floor needs to be filled with compacted stone before a concrete floor is poured.
A view of the inside with some of the interior walls installed.
A view looking out the back of the house.
A view of the back of the house after 3 days of framing.
View of the back side of the house in the morning.
A crane was brought in to lift a heavy steel I-beam and position it in the garage area.
Setting the I-beam in place. This I-beam spans the length of the garage area and will support the second floor living space over the garage.
With the I-beam in place the crew installed the floor joists for the second floor. The garage floor needs to be filled with compacted stone before a concrete floor is poured.
A view of the inside with some of the interior walls installed.
A view looking out the back of the house.
A view of the back of the house after 3 days of framing.
16 January 2014
Hopkins' New House - Day 2
The second day of framing on Brian & Tish Hopkins' new house started off colder with a dusting of snow but the framing crew had most of the first floor exterior walls up by 11:00AM..
A view of the back, east side, of the house.
With some of the interior walls in place the framing crew works on finishing the exterior in the front of the house next to the garage.
The framing crew starts to work on the placement of the floor joists for the second as the afternoon sun starts to set.
By the afternoon it was warm enough for some of the crew to work in short sleeved shirts.
A view of the back, east side, of the house.
With some of the interior walls in place the framing crew works on finishing the exterior in the front of the house next to the garage.
The framing crew starts to work on the placement of the floor joists for the second as the afternoon sun starts to set.
By the afternoon it was warm enough for some of the crew to work in short sleeved shirts.
15 January 2014
Hopkins' New House
With the basement walls installed on Monday and a truck load of materials delivered yesterday, the activity at Brian & Tish Hopkins' new house picked up today as the construction crew arrived on site to start the framing. By 9:30AM the crew had the sill plate and main beam installed.
By 12:00 the floor joists and most of the rim joist were in place.
Around 1:00PM another load of materials was delivered.
By 3:30PM the sub-floor was down and the crew was building the first section of the side walls.
4:00PM and the first wall section was lifted into place.
By 12:00 the floor joists and most of the rim joist were in place.
Around 1:00PM another load of materials was delivered.
By 3:30PM the sub-floor was down and the crew was building the first section of the side walls.
4:00PM and the first wall section was lifted into place.
Subscribe to: