20 January 2014

Hopkins' New House - Day 4

The weekend brought a couple inches of snow and the framing crew was busy working on Brian & Tish Hopkins' new house



Today is the forth day of work by the framing crew and by 10:00AM they had the second floor exterior walls in place and ready to start on the roof.



The colder weather over the weekend firmed up the ground and some rough grading was done to prepare for a crane and trucks of roof trusses.



By 4:00PM the roof trusses were in place and the crew was installing the roof sheathing.





A view of the back side of the house with roof sheathing installed.