The weather turned colder over night and there was a light dusting of snow but the framing crew didn't slow down on the construction of Brian & Tish Hopkins' new house.
By 11:00AM they had installed more roof rafters and sheathing on the front side of the house.
Roof framing on the north end of the house at 11:00AM.
By 4:00PM the crew had finished the roof framing and some more of the interior walls.
21 January 2014