There wasn't any activity at Brian & Tish Hopkins' new house yesterday due to the cold weather but the framing crew was back today. More building materials arrived today, including bundles of roofing shingles which were stacked in the roof awaiting a roofing crew.



By 1:00PM the temporary stairs were installed to make access the second floor easier.



Interior walls on the second floor were going in but there was still some open space at 1:00PM.



By 4:30PM most of the second floor walls were in place.



The room layouts are starting to take shape as the tub and shower units are positioned in the rough openings.



A stack of wall studs in one of the front bedrooms dwindles as the new walls go up.



The windows are starting to go in.