With the basement walls installed on Monday and a truck load of materials delivered yesterday, the activity at Brian & Tish Hopkins' new house picked up today as the construction crew arrived on site to start the framing. By 9:30AM the crew had the sill plate and main beam installed.
By 12:00 the floor joists and most of the rim joist were in place.
Around 1:00PM another load of materials was delivered.
By 3:30PM the sub-floor was down and the crew was building the first section of the side walls.
4:00PM and the first wall section was lifted into place.
15 January 2014