14 April 2011

Pad Construction - Day 16

Yesterday's rain turned the clay soil to a muddy mess ...



Today's sunshine (and lack of rain overnight) allowed the crew to make some progress.



Greenway Engineering was on site for an E&S (erosion and sediment) inspection.



Two CAT D8s double teamed the dirt moving as they started creating the level section of the northeast corner of the drill pad.



Looking southeast from the stream crossing the lower side of the hillside is starting to raise.



View of the pad construction from across the valley. Click on image to enlarge view.