28 April 2012

Pipeline Construction

The welding of sections of 24 inch pipe completed and passed the X-ray inspection.



The completed sections of welded pipe were moved out of the welding area to allow the excavators to start digging the trenches to bury the pipe in.



While the trenches are being done, another crew will sandblast and coat the welded joints.



An excavator works on digging out the bore pipe so it can be cut off and welded to sections of pipeline that will cross the wetland area.