22 May 2012

Pipeline Construction

Today was another busy day of pipeline activity on both pipelines.

Wesauking Pipeline
The 12 inch valve/"pig receiver" assembly was delivered and positioned.




This assembly connects the 12 inch Wesauking Pipeline with the 24 inch Wilmot Pipeline. Since the flow of gas on the Wesauking Pipeline only travels in one direction to this connection, the assembly can only receive "pigs".



On the west side of Joyce Road, the pipeline reclamation of the Wesauking Pipeline on Maureen Brady's property is moving along. The topsoil has been regraded and the crew is busy smoothing out the surface.



Reseeding the pipeline right-of-way section next to our barn.






The wetland area and back field of Maureen Brady's.



Wilmot Pipeline
Th connector between the 20 inch and 24 inch "pig launchers" was installed.





Making some finial adjustments to the position of the 20 inch "pig launcher".





No comments: